KVDT2 project: June 4 decision on Dhaya Maju's injunction bid


30 Apr 2021 / 19:34 H.
Pix for illustration purposes.
KUALA
LUMPUR: The High Court here today has fixed June 4 to decide on Dhaya Maju LTAT Sdn Bhd’s injunction application to restrain the government and Keretapi Tanah Melayu Berhad (KTMB) from instructing the company to stop work on the Klang Valley Double Tracking Phase 2 (KVDT2) project site.
Judge Datuk Lim Chong Fong fixed the date after hearing submissions on Dhaya Maju’s injunction application by counsel Khoo Guan Huat, who is representing Dhaya Maju as the plaintiff and senior federal counsel Asliza Ali acting for the government, Transport Minister Datuk Seri Dr Wee Ka Siong, Keretapi Tanah Melayu Berhad (KTMB) and engineering consulting company, Opus Consultants (M) Sdn Bhd as defendants. ....

Lembaga Tabung Angkatan Tentera , Pakatan Harapan , Dhaya Maju , Chong Fong , Keretapi Tanah Melayu Berhad , M Sdn Bhd , Khoo Guan Huat , Idrus Harun , Sdn Bhd , Asia Sdn Bhd , Asliza Ali , Zafrul Abdul Aziz , High Court , Klang Valley Double Tracking Phase , Datuk Lim Chong Fong , Opus Consultants , Justice Lim , Attorney General Tan Sri Idrus Harun , Government Proceedings Act , Contract Under Review , Dhaya Maju Infrastructure , Companies Act , Agreement Settlement , தயா மஜு , சோங் பொங் , மீ ஸ்டன் ப்ட் ,

Klang Valley double tracking project: June 4 decision on Dhaya Maju's injunction bid | Malaysia


Friday, 30 Apr 2021 08:02 PM MYT
On October 27 last year, Dhaya Maju LTAT filed a suit against the government, Datuk Seri Wee Ka Siong, KTMB and Opus Consultants respectively as defendants one to four on the termination of its contract for KVDT2 project. Reuters pic
Subscribe to our Telegram channel for the latest updates on news you need to know.
KUALA LUMPUR, April 30 The High Court here today has fixed June 4 to decide on Dhaya Maju LTAT Sdn Bhd’s injunction application to restrain the government and Keretapi Tanah Melayu Berhad (KTMB) from instructing the company to stop work on the Klang Valley Double Tracking Phase 2 (KVDT2) project site. ....

Kuala Lumpur , Lembaga Tabung Angkatan Tentera , Pakatan Harapan , Dhaya Maju , Tengku Zafrul Abdul Aziz , Chong Fong , Keretapi Tanah Melayu Berhad , M Sdn Bhd , Khoo Guan Huat , Sdn Bhd , Idrus Harun , Asia Sdn Bhd , Asliza Ali , High Court , Datuk Seri Wee Ka Siong , Opus Consultants , Klang Valley Double Tracking Phase , Datuk Lim Chong Fong , Justice Lim , Attorney General Tan Sri Idrus Harun , Attorney General , Government Proceedings Act , Contract Under Review , Dhaya Maju Infrastructure , Companies Act , Agreement Settlement ,

Dhaya Maju LTAT fails to gain ownership of KVDT2 project site


KUALA LUMPUR (Bernama): Dhaya Maju LTAT Sdn Bhd has failed to gain ownership of the Klang Valley Double Tracking Phase 2 (KVDT2) project site to continue work, which has been ordered to be taken over by the government.
Senior Federal Counsel (SFC) Asliza Ali, who is representing the government and Transport Minister Datuk Seri Dr Wee Ka Siong, as defendants told Bernama that Justice Lim Chong Fong rejected the application of Dhaya Maju LTAT as the plaintiff for the ownership of the project site to be given to the company during case management in his chambers on Tuesday (April 20).
The proceeding was also conducted by SFC Azlin Sabtu while counsel Ashok Ranai acted on behalf of the contractor firm. ....

Kuala Lumpur , Lembaga Tabung Angkatan Tentera , Pakatan Harapan , Chong Fong , Keretapi Tanah Melayu Berhad , M Sdn Bhd , Sdn Bhd , Asia Sdn Bhd , Asliza Ali , Ashok Ranai , Azlin Sabtu , Zafrul Abdul Aziz , High Court , Dhaya Maju , Klang Valley Double Tracking Phase , Federal Counsel , Justice Lim Chong Fong , High Court Judge Noorin Badarudin , Justice Noorin , High Court April , Justice Lim , Opus Consultants , Contract Under Review , Dhaya Maju Infrastructure , Companies Act , Agreement Settlement ,