Second stage of Swansea channel dredging starts, 13,000 cubic metres of sand to be removed by July. NSW Labor announces 10-year strategy for local boaters.
Stay updated with breaking news from Drop Over. Get real-time updates on events, politics, business, and more. Visit us for reliable news and exclusive interviews.
Second stage of Swansea channel dredging starts, 13,000 cubic metres of sand to be removed by July. NSW Labor announces 10-year strategy for local boaters.
The first stage of dredging the Swansea Channel has been completed, with 16,690 cubic metres of sand moved so far.
The first stage of dredging the Swansea Channel has been completed, with 16,690 cubic metres of sand moved so far.
The first stage of dredging the Swansea Channel has been completed, with 16,690 cubic metres of sand moved so far.
The first stage of dredging the Swansea Channel has been completed, with 16,690 cubic metres of sand moved so far.