Judge denies injunction to stop CMP from starting transmission corridor work
Judge rejects bid to keep CMP from starting work on transmission corridor CMP says construction of the 145-mile corridor will likely begin sometime in January. Share A federal judge has denied a motion for a preliminary injunction that would have prevented Central Maine Power Co. from beginning construction on a 145-mile transmission line project to bring hydropower from Quebec to the New England power grid. U.S. District Judge Lance E. Walker issued his 49-page ruling Wednesday afternoon, rejecting the civil action filed by plaintiffs Sierra Club Maine, the Natural Resources Council of Main...