HDB completes all 5 projects delayed by contractor Greatearth winding up
About 3,000 affected flat owners got their keys between two and 12 months after their original estimated completion date.
Stay updated with breaking news from Marsiling Grove. Get real-time updates on events, politics, business, and more. Visit us for reliable news and exclusive interviews.
About 3,000 affected flat owners got their keys between two and 12 months after their original estimated completion date.
As at Sept 30, majority of residents at West Coast ParkView in Clementi had collected keys. Read more at straitstimes.com.
The national development minister said that Singapore was "turning the corner" with regard to project delays.
Singapore News - The wait for some flat owners is over, with work completed ahead of revised deadlines in two of the five... Read more at www.tnp.sg
The completion dates of the five projects had each been delayed by about three months. . Read more at straitstimes.com.