Energean's first gas from Israel fields faces possible delays | Hellenic Shipping News Worldwide
Energean’s first gas from Israel fields faces possible delays Energean said on Thursday the first gas from its flagship Israeli fields, due to start flowing at the end of this year, could slip by two to three months. The company said this was due to delays to increasing the workforce that is building its floating production, storage and offloading vessel in Singapore, which was due to sail to Israel towards the end of the third quarter 2021. Energean said this was primarily due to Covid-19 working conditions. “Energean and its contractors are in ongoing discussions to achieve the required...