Judge Cancels Montana Gas Plant Permit Over Climate Impacts
A judge canceled the air quality permit for a natural gas power plant that's under construction along the Yellowstone River in Montana citing worries over
Source: insurancejournal.com
Stay updated with breaking news from Michael Moses. Get real-time updates on events, politics, business, and more. Visit us for reliable news and exclusive interviews.
A judge canceled the air quality permit for a natural gas power plant that's under construction along the Yellowstone River in Montana citing worries over
The $250 million plant would operate for at least 30 years.
The $250 million plant would operate for at least 30 years.
NorthWestern Corporation d/b/a NorthWestern Energy (Nasdaq: NWE) appreciates that Montana District Court Judge Michael Moses supported the majority of the
The ruling from Yellowstone County District Judge Michael Moses was a victory for landowners near the project along Thiel Road south of Laurel.