SC utility's falling fuel bills are offset by other big-ticket expenses
Santee Cooper's spending plan for next year totals $2.6 billion, up 13 percent from 2023.
Stay updated with breaking news from Moncks Corner Based. Get real-time updates on events, politics, business, and more. Visit us for reliable news and exclusive interviews.
Santee Cooper's spending plan for next year totals $2.6 billion, up 13 percent from 2023.
The S.C. Department of Health and Environmental Control cited the state-owned utility Santee Cooper over one of its boilers at the Winyah Generating Station exceeding the allowable limits of sulfur dioxide over a period of more than 130 days in 2021, according to a consent order released by the agency.
Critics say the plan leans too heavily on a gas-fired power plant the utility is looking to build to replace its retiring coal generators.
The S.C. Public Service Commission will review the $17 million deal on Sept. 5 in Columbia.
It's still unclear whether it will be allowed to recoup the funds from ratepayers retroactively.