State regulators to hear Plant Vogtle progress report after nuclear expansion stalled again
Georgia Public Service Commission is set to hold hearing on July 27, 2023 for Georgia Power's $35 billion Plant Vogtle nuclear expansion.
Stay updated with breaking news from Oglethorpe Power. Get real-time updates on events, politics, business, and more. Visit us for reliable news and exclusive interviews.
Georgia Public Service Commission is set to hold hearing on July 27, 2023 for Georgia Power's $35 billion Plant Vogtle nuclear expansion.
/PRNewswire/ -- Today, Georgia Power announced completion of another important step in the startup and operation of the new nuclear units at the Vogtle 3 & 4...
Georgia Power says that all 364 inspections, tests and analyses have been performed and all acceptance criteria, known as ITAACs, have been met on Vogtle unit 4 and the documentation submitted to the US Nuclear Regulatory Commission.
A big step toward bringing Unit 4 at Plant Vogtle online was completed this week when Georgia Power sent test results to the Nuclear Regulatory Commission.