After a gap of 12 years the Maharashtra government has given a go-ahead to the Pavana pipeline project. Once completed, it will help ease the water crisis of Pimpri-Chinchwad. ....
The decision to finally lay the Pavana pipelines 12 years after it was stalled came a day after the Maharashtra government lifted the ban on the implementation on Monday. ....
The Pavana pipeline project involves laying a direct 36-km closed pipeline from the Pavana dam in Maval taluka to Ravet in Pimpri-Chinchwad. 'The project cost has gone up from Rs 400 crore to Rs 1,000 crore after the work was stalled in 2011. ....
PCMC Joint City Engineer Shrikant Savane said, “The PCMC has been pursuing the issue with the state government for some time. We hope some solution will be found soon.” ....