With project stuck since 2014, UP RERA allows Ajnara Realtech to complete remaining work in 24 months
According to a site inspection report carried out last year, the overall physical progress of the Ajnara Le Garden Phase-3 was only 35 per cent, in which 585 residential units are being developed in four towers. Presently, 476 units have been sold and 109 units are yet to be sold.