Thialf сompletes removal of Sable Project offshore facilities
Thialf Ñompletes removal of Sable Project offshore facilities Earlier this month, Heerema’s Thialf completed the eight month long campaign to remove the Sable Project’s offshore facilities on behalf of client ExxonMobil Canada. Thialf arrived in Canada in early April and mobilized to the Sable Field on May 1 to begin executing a sequence of separate lifts of platform components using a reverse-installation method. The campaign entailed the Engineering, Preparation, Removal, and Disposal (EPRD) of seven platform topsides, seven jackets and 22 conductors. A total of five barge loads ca...