Great progress has been made on the new Delia School, and it is on track to open to students on schedule. Prairie Land School Division broke ground on the project in September of last year, and the managing contractor Shunda of Red Deer has been making steady progress on the new school project. “To date, we have 95 per cent of the structural steel up and in place. Obviously, our masonry is done for now on the gym,” said Site superintendent Brian Antonsen. “The roofers are on site and are about 30 per cent complete.” He said the masonry and siding contractors are also on-site installin...