Bridge connecting Binondo, Intramuros 88% complete
Binondo - Intramuros Bridge (Photo courtesy of DPWH MANILA - The Binondo-Intramuros Bridge is nearing completion, with the overall progress now at 88.63 percent, the Department of Public Works and Highways (DPWH) reported in a news release on Friday. Undersecretary Emil Sadain reported to DPWH acting Secretary Roger Mercado that with the completed basket-handle tied steel arch main bridge over Pasig River, the target finish is by the first half of 2022. The bridge was originally planned to open to motorists by the end of 2021 but the DPWH had to push back the timeframe to relocate public and p...