The US Army Corps has politely asked a state environmental agency to stand down—for now—on its questions about the quality of sand that would be scooped from Scusset Beach and deposited on Town Neck Beach.
Michael S. Riccio, the Army Corps’ project manager for the New England District, said in a recent email to Town Manager George H. (Bud) Dunham that the Corps had erred in asking the Massachusetts Office of Coastal Zone Management (CZM) to weigh in on the consistency of Scusset sand.
Mr. Riccio said that although—in seeking the many permits needed before the Army Corps can dredge and deposit almost 400,000 cubic yards of sand on badly eroded Town Neck Beach—the Army Corps asked CZM for a “consistency determination” the request came too soon in the lengthy process.

Related Keywords

Cape Cod Canal ,Massachusetts ,United States ,Scusset Beach ,Town Neck ,Lisa Berry Engler ,Michaels Riccio ,Army Corp ,Massachusetts Office Of Coastal Zone Management ,Us Army Corps ,Army Corps ,New England District ,Town Manager George ,Massachusetts Office ,Coastal Zone Management ,Town Neck Beach ,Public Notice ,Design Phase ,Sandwich Erosion ,Army Corps Of Engineers ,Zm Consistency Determination ,Hand ,Geology ,Military ,Company ,கேப் காட் கால்வாய் ,மாசசூசெட்ஸ் ,ஒன்றுபட்டது மாநிலங்களில் ,நகரம் கழுத்து ,மைக்கேல்ஸ் ரிச்சியோ ,இராணுவம் கார்ப் ,மாசசூசெட்ஸ் அலுவலகம் ஆஃப் கடலோர ஸோந் மேலாண்மை ,எங்களுக்கு இராணுவம் கார்ப்ஸ் ,இராணுவம் கார்ப்ஸ் ,புதியது இங்கிலாந்து மாவட்டம் ,நகரம் மேலாளர் ஜார்ஜ் ,மாசசூசெட்ஸ் அலுவலகம் ,கடலோர ஸோந் மேலாண்மை ,நகரம் கழுத்து கடற்கரை ,பொது அறிவிப்பு ,வடிவமைப்பு கட்டம் ,மற்றும் ,

© 2025 Vimarsana

vimarsana.com © 2020. All Rights Reserved.