BTSC defers Pink, Yellow Line tests
published :
1 Jul 2021 at 04:00
The Bangkok Mass Transit System Plc (BTSC) has postponed test-run plans for the Pink and Yellow Line extensions following the temporary closure of construction worker campsites across the city to curb Covid-19 transmissions.
Surapong Laoha-unya, CEO of the BTSC, on Wednesdy said construction work on the Pink Line's Khae Rai-Min Buri section and the Yellow Line's Lat Phrao-Samrong section were 70-80% complete.
Only minor work, such as electrical system installation and fittings, remained unfinished.
Originally, the 30-kilometre Yellow Line was to open by year's end and the 34.5-kilometre Pink Line was expected to be running around March or April next year.

Related Keywords

Bangkok ,Krung Thep Mahanakhon ,Thailand ,Min Buri ,Surapong Laoha Unya ,Kittikorn Tanpao ,Khae Rai ,Mass Rapid Transit Authority Of Thailand ,Bangkok Mass Transit System Plc ,Yellow Line ,Pink Line ,Khae Rai Min Buri ,Lat Phrao Samrong ,Mass Rapid Transit Authority ,Emergency Decree ,Public Administration ,Emergency Situations ,பாங்காக் ,தாய்லாந்து ,நிமிடம் புரி ,நிறை விரைவான போக்குவரத்து அதிகாரம் ஆஃப் தாய்லாந்து ,பாங்காக் நிறை போக்குவரத்து அமைப்பு ப்ல் ,மஞ்சள் வரி ,இளஞ்சிவப்பு வரி ,நிறை விரைவான போக்குவரத்து அதிகாரம் ,அவசரம் ஆணை ,அவசரம் சூழ்நிலைகள் ,

© 2025 Vimarsana

vimarsana.com © 2020. All Rights Reserved.