Giant reconfiguring of I-80, I-380 interchange on schedule
LEE HERMISTON, The Gazette
FacebookTwitterEmail
CORALVILLE, Iowa (AP) — While there were concerns a year ago about progress on the $387 million project to reconfigure the Interstate 80-Interstate 380 interchange, the Iowa Department of Transportation said this month that the massive undertaking is on schedule and on budget.
“A year ago I felt like we were behind overall,” said Hugh Holak, construction engineer with Iowa DOT. “The summer of 2020 was actually a very dry year. They were able to get a lot more work done than I was anticipating.”
Iowa DOT construction manager Linda Narigon said 2019 was a “very, very wet year” and said crews were pulled from the project to build emergency levees to fight flooding on either side of the state.

Related Keywords

Cedar Rapids ,Iowa ,United States ,Coralville ,Linda Narigon ,Kelly Hayworth , ,Ireland Avenue ,City Administrator Kelly Hayworth ,Forevergreen Road ,Coral Ridge Avenue ,Hugh Holak ,Steindler ,I 80 ,Hi 380 ,North America ,Highway 6 ,Tiffin ,Iowa Department Of Transportation ,Yap ,Cedar Rapids Gazette ,Exchange Freeway Interchange ,Highway 218 ,Orthopedics ,சிடார் ரேபிட்கள் ,ஐயுவா ,ஒன்றுபட்டது மாநிலங்களில் ,பவளப்பாறை ,கெல்லி ஹேவொர்த் ,ஐயர்ல்யாஂட் அவென்யூ ,பவளம் ரிட்ஜ் அவென்யூ ,ஸ்டைண்ட்லர் ,நான் ,வடக்கு அமெரிக்கா ,சிற்றுண்டி ,ஐயுவா துறை ஆஃப் போக்குவரத்து ,அப் ,சிடார் ரேபிட்கள் கஸெட் ,பரிமாற்றம் தனிவழி பரிமாற்றம் ,எலும்பியல் ,