Next-generation US nuclear sub facing cost overruns, delays
By Tony Capaccio Bloomberg,Updated December 23, 2020, 4:09 p.m.
Email to a Friend
The US Navy’s plan to deliver the first vessel in its $128 billion next-generation submarine program on time is at risk by a dependence on inexperienced contractors with spotty quality control track records, according to a congressional watchdog.
The Government Accountability Office, in a restricted Nov. 6 report to the Pentagon and congressional defense committees, said the design contract for the first vessel in the Columbia-class sub fleet being built by General Dynamics Corp. could have a cost overrun of as much as 14 percent, or $384 million.

Related Keywords

Virginia ,United States ,Elizabeth Power ,Huntington Ingalls Industries Inc ,General Dynamics ,Bloomberg News ,Official Use Only ,Cold War ,General Dynamic Groton ,Quonset Point ,Naval Sea Systems Command ,வர்ஜீனியா ,ஒன்றுபட்டது மாநிலங்களில் ,எலிசபெத் பவர் ,ஹண்டிங்டன் இங்காள்லஸ் தொழில்கள் இன்க் ,ஜநரல் இயக்கவியல் ,ப்ளூம்பெர்க் செய்தி ,அதிகாரி பயன்பாடு மட்டும் ,குளிர் போர் ,ஜநரல் மாறும் கிறோத்தொன் ,க்வாந்‌ஸெட் பாயஂட் ,கடற்படை கடல் அமைப்புகள் கட்டளை ,

© 2025 Vimarsana

vimarsana.com © 2020. All Rights Reserved.