VINCENT — General contracts for multiple building projects were awarded during Monday night’s meeting of the Warren Local Schools Board of Education.
Elementary school demolition
A resolution passed awarding contracts for the demolition of Little Hocking and Warren elementaries to Raze International Inc. of Shadyside.
The contract for the Little Hocking school demolition was $325,190, while the former Warren Elementary will be torn down at a cost of $202,190.
“They will start that process Jan. 1. They’ve been on site already getting prepared,” said Superintendent Kyle Newton. “They’re ready to go. I know they’re going to be working on that right away.”

Related Keywords

Little Hocking ,Ohio ,United States ,Shadyside ,Warren High School ,Bob Crum ,Sid Brackenridge ,Kyle Newton ,Warren Middle School ,Rw Setterlin Building Company Of Columbus ,Raze International Inc ,Motz Group Of Cincinnati ,Ohio Facilities Construction Commission ,Warren Local Schools Board ,Raze International ,Warren Elementary ,Superintendent Kyle ,Building Company ,Ohio Facilities Construction ,President Bob Crum ,Motz Group ,கொஞ்சம் ஹாக்கிங் ,ஓஹியோ ,ஒன்றுபட்டது மாநிலங்களில் ,நிழல் ,வாரன் உயர் பள்ளி ,பாப் கிரும் ,சீட் பிராக்கென்ரிட்ஜ் ,கைல் நியூட்டன் ,வாரன் நடுத்தர பள்ளி ,ரேஸ் சர்வதேச இன்க் ,மோதிஜ் குழு ஆஃப் ஸிந்ஸந்யாடீ ,ஓஹியோ வசதிகள் கட்டுமானம் தரகு ,வாரன் உள்ளூர் பள்ளிகள் பலகை ,ரேஸ் சர்வதேச ,வாரன் தொடக்க ,கண்காணிப்பாளர் கைல் ,கட்டிடம் நிறுவனம் ,ஓஹியோ வசதிகள் கட்டுமானம் ,ப்ரெஸிடெஂட் பாப் கிரும் ,மோதிஜ் குழு ,

© 2024 Vimarsana

vimarsana.com © 2020. All Rights Reserved.