📰 Full Capacity Using News
Full Capacity Using News Today
Fast, Ad-Free News Updates
Stay updated with breaking news from Full Capacity Using. Real-time updates on events, politics, business and more.
January 30, 2024
Here we go again. Freeport LNG’s export terminal with three liquefaction “trains” shut down in June 2022 after an explosion and fire (see Explosion Rocks Freeport LNG Export Plant – Offline for 3 Weeks). What was initially thought to be a three-week outage lasted for ten months! The plant finally returned online in March of
December 15, 2023
Freeport LNG’s export terminal with three liquefaction “trains” shut down in June 2022 after an explosion and fire (see Explosion Rocks Freeport LNG Export Plant – Offline for 3 Weeks). What was initially thought to be a three-week outage lasted for ten months. The plant finally returned online in March of this year (see Freeport
November 27, 2023
Freeport LNG’s export terminal with three liquefaction “trains” shut down in June 2022 after an explosion and fire (see Explosion Rocks Freeport LNG Export Plant – Offline for 3 Weeks). What was initially thought to be a three-week outage lasted for ten months! The plant finally returned online in March of this year (see Freeport
October 30, 2023
Freeport LNG’s export terminal with three liquefaction “trains” shut down in June 2022 after an explosion and fire (see Explosion Rocks Freeport LNG Export Plant – Offline for 3 Weeks). What was initially thought to be a three-week outage lasted for ten months! The plant finally returned online in March of this year (see Freeport
October 5, 2023
Freeport LNG’s export terminal with three liquefaction “trains” shut down in June 2022 after an explosion and fire (see Explosion Rocks Freeport LNG Export Plant – Offline for 3 Weeks). What was originally thought to be a three-week outage lasted for ten months! The plant finally returned online in March of this year (see Freeport
August 1, 2023
The U.S. Energy Information Administration (EIA) is reporting feed gas (natural gas) delivered to LNG export facilities for the first six months of this year hit a new all-time average high of 12.8 Bcf/d (billion cubic feet per day). We hit that high after the Freeport LNG facility finally came back online following a June
June 14, 2023
Freeport LNG's export terminal with three liquefaction "trains" shut down in June 2022 after an explosion and fire (see Explosion Rocks Freeport LNG Export Plant – Offline for 3 Weeks). What was originally thought to be a three-week outage lasted for ten months! The plant finally returned online at the end of March this year
May 2, 2023
U.S. LNG (liquefied natural gas) exports are hitting new highs each month now that the Freeport LNG facility came back online in March (see Freeport LNG Plant Back to Full Capacity Using 2.1 Bcf/d of NatGas). March saw a new, all-time high export of 7.80 million tonnes of LNG (see U.S. LNG Exports Hit New
April 5, 2023
Freeport LNG is back online, sucking up 2.1 (or more) billion cubic feet per day (Bcf/d) of natural gas, some of it from the Marcellus/Utica, exporting LNG to other countries. Freeport was out of commission following an explosion and fire in June 2022 until several weeks ago (see Freeport LNG Plant Back to Full Capacity