March 25, 2022
Under the Insolvency and Bankruptcy Code (IBC), the NCLT has appointed Hitesh Goel as the insolvency resolution professional (IRP). Supertech Declared Bankrupt by NCLT, Fate of Over 25,000 Homebuyers’ Lays Hanging.
February 28, 2022
The Noida authority on Monday informed the Supreme Court that Supertech 40-story twin towers will be demolished on May 22, reported news agency ANI.
February 28, 2022
Supertechs twin towers to be demolished by May 22: Noida authority to SC - A bench of Justices DY Chandrachud and Surya Kant also informed that the entire debris would be removed by August 22 from the site by M/S Edifice.
February 28, 2022
On February 7, the Supreme Court had directed that the demolition of the twin towers built by real-estate major Supertech Ltd in violation of norms at its Emerald Court project in Noida should start within two weeks.
February 28, 2022
The Noida authorities also added that all debris of the twin 40-storey towers will be removed by August 22.
February 9, 2022
Resources can be mobilised immediately for demolition of real estate group Supertech's illegal 40-storey twin-towers so that the process to raze them can begin from February 20, the Noida Authority said to Supertech and Edifice Engineering.
February 8, 2022
The apex court ordered to begin the demolition process in 2 weeks. Supertechโs counsel informed the court during the hearing that an email was received from the Noida authority on February 5 intimating that necessary clearances for the demolition had been received.
February 7, 2022
SC directed NOIDA CEO will convene meeting of all concerned agencies within 72 hours to finalise the schedule for demolition of twin 40-storied towers of Supertech Emerald Court.ย
February 7, 2022
The Supreme Court on Monday said the demolition work for the two 40 story towers constructed by Supertech in Noida, will begin in two weeks. A bench headed by Justice D Y Chandrachud directed the Noida CEO to commence the demolition work within two weeks, and also convene a meeting with all agencies concerned, including GAIL, within 72 hours to finalise the schedule and the
February 7, 2022
Noida Authority has been instructed by the Supreme Court to present a plan for the demolition of the twin towers, part of Supertech's Emerald Court project, within 72 hours.