All Koper-Divača review procedures complete as Strabag's appeal rejected


Ljubljana – The National Review Commission has rejected the appeal by the Austrian builder Strabag against the decision by the state-owned company 2TDK to pick a Slovenian-headed consortium as the contractor for the Divača-Črni Kal section of the new railway to the port of Koper. This ends all review procedures related to the project.
Strabag appealed in late March the decision by 2TDK to entrust the section to Kolektor CPG in partnership with the Turkish companies Yapi Merkezi and Özaltin as the cheapest bidder.
The cost of the section was capped at EUR 472 million. The Kolektor CPG-led consortium offered to build it for EUR 403.6 million, while Strabag submitted a EUR 463.5 million bid in partnership with the German company Ed Züblin and Turkish Gülermak Agir.

Related Keywords

Germany , Ljubljana , Slovenia General , Slovenia , Austria , Turkey , Turkish , German , Austrian , Yapi Merkezi , Strabag , National Review Commission , Review Commission , ஜெர்மனி , ஸ்லோவேனியா ஜநரல் , ஸ்லோவேனியா , ஆஸ்ட்ரியா , வான்கோழி , துருக்கிய , ஜெர்மன் , ஆஸ்திரேலிய , தேசிய விமர்சனம் தரகு , விமர்சனம் தரகு ,

© 2025 Vimarsana