Casting of CCLEX's girders already complete – Manila

Casting of CCLEX's girders already complete – Manila Bulletin


Published May 26, 2021, 8:49 AM
CEBU CITY—The Cebu-Cordova Link Expressway (CCLEX) is already 70.33 percent complete.
As of April 2021, the Cebu-Cordova Link Expressway Corp. (CCLEC), reported that the overall Engineering, Procurement, and Construction (EPC) progress of the 8.5-kilometer CCLEX is at 74.86 percent.
With the progress, CCLEX is seen to be substantially completed by the end of 2021 and to open to motorists in the first quarter of 2022.
ALMOST COMPLETE. The picturesque Cebu-Cordova Link Expressway (CCLEX) is already 70% complete and is expected to be operational early 2022. (Photo courtesy of CCLEC)
In its project updates, CCLEC reported construction milestone with the completion of the casting of all 446 Nebraska University (NU) girders required for the entire stretch of CCLEX.

Related Keywords

Philippines , Mactan , Masbate , Mactan Island , Lapu , Nebraska , United States , , Nebraska University , Properties In Cebu City To Mactan Island , Cordova Link Expressway Corp , Cebu Cordova Link Expressway , South Road Properties , Cebu City , Marcelo Fernan Bridge , பிலிப்பைன்ஸ் , நெப்ராஸ்கா , ஒன்றுபட்டது மாநிலங்களில் , நெப்ராஸ்கா பல்கலைக்கழகம் , கோர்டோவா இணைப்பு அதிவேக நெடுஞ்சாலை கார்ப் , ஸிபூ கோர்டோவா இணைப்பு அதிவேக நெடுஞ்சாலை , தெற்கு சாலை ப்ராபர்டீஸ் , ஸிபூ நகரம் , மார்செலோ ஃபெர்னன் பாலம் ,