Article content The pedestrian crossing under the new $391-million Tawatinâ Bridge was supposed to be complete by May 2019, but that deadline went off track when a car-sized concrete slab was found in the river during bridge construction. In an update to Postmedia, TransEd communications manager Dallas Lindskoog said the river crossing should open in line with LRT service, and maybe even a bit before. We apologize, but this video has failed to load. Try refreshing your browser, or Delayed Valley Line LRT pedestrian bridge across the river not expected to open before snow hits Back to video There isn’t a set timeline for opening the 13 km line, but Lindskoog said the team is working toward getting the line ready by the end of the year, about one year after the initial opening plan of December 2020.