Delays push back completion date of Glass Avenue work The Daily Jeffersonian Village Administrator Brennan Dudley recently told Byesville Village Council members that work continues on the Glass Avenue culvert project. The project, which was scheduled for completion on April 9, has run into some delays. According to Dudley there were some issues with personnel changes for the contractor. "We did make some concessions for the paving portion of the project and also repair of the alley between the Creek and North Sixth Street," Dudley said. "We will do those two things, and, in return, we will not be charged by the contractor. We can do those much better and more efficient I think and at less cost than what the contractor can do."