the kill line to the helix producer and choke line to the q 4000. okay? last week as you remember we removed the stub of the riser pipe and we put in what we called a flange spool. on top of that what will happen, which was significant, is we've now seeded the capping stack here and basically it has three rams, a mini blowout preventer, also has a kill line and a choke line. okay? so you basically have a small bop on top of the larger bop that is legacy to the deepwater horizon. here is how we intend to do the well integrity test. we will slowly take down production from the q 4000 and the helix producer later on today to the point where they are not producing anymore. that will force the oil up through the ploeout preventer into the capping stack. at that point the kill line, the choke line, and the top of the stack will be open. there will be product releasing from there. that's the reason we know we have the skimmers and additional