EXPLAINER: 4th Mactan-Cebu bridge location opposed by Lapu-L

EXPLAINER: 4th Mactan-Cebu bridge location opposed by Lapu-Lapu business sector, city government. Is their objection being heard by Malacañang?


April 23, 2021
WHAT WENT BEFORE: [] March 6, 2019: Japanese consultants from Japan International Cooperation Agreement (Jica) presented a preliminary survey to DPWH-Central Visayas for the fourth 3.3-kilometer Cebu-Mactan bridge.
A second component of the Bridge 4 project is a Mandaue City 4.9-kilometer coastal road, an extension of the proposed Metro Cebu circumferential road or proposed Mandaue-Liloan diversion road to divert traffic from the city center through a bypass road.
The project is scheduled to be completed in January 2028 "when all facilities are put into service." Both bridge and road are estimated to cost P79.5 billion (from the original P56 billion).
[] February 23, 2020: Lapu-Lapu City Mayor Junard "Ahong" Chan announced he would propose to Malacañang the change of the location of the bridge on his city's side, a little farther from the Marcelo Fernan Bridge.

Related Keywords

Mandaue , Philippines , Lapu , Japan , Barangay , Pangasinan , Lapu City , Malaca , Mandaue City , Mambaling , Quezon , Mactan , Masbate , Japanese , Dpwh Central Visayas , Rodrigo Duterte , Junard Ahong Chan , Lapu City Development Council , Japan International Cooperation Agreement Jica , Japan International Cooperation Agreement , Central Visayas , Metro Cebu , Lapu City Mayor Junard , Marcelo Fernan , President Rodrigo Duterte , Lapu Mayor Chan , Executive Secretary Salvador Medialdea , Marina Mall , Cansaga Bay , Mayor Chan , Fernan Bridge , Barangay Ibo , President Duterte , பிலிப்பைன்ஸ் , ஜப்பான் , பங்கசினன் , கயீஸந் , ஜப்பானிய , மைய விசயாஸ் , மெட்ரோ ஸிபூ , மார்செலோ ஃபெர்னன் , மெரினா மால் , மேயர் சான் , ஃபெர்னன் பாலம் ,