The Falmouth Select Board on Monday, February 22, approved hiring a consultant to assist with the creation of bid documents necessary for the disposition of the two wind turbines at the wastewater treatment plant site on Blacksmith Shop Road. Attorney Christopher W. Morog told the board that Massachusetts General Law allows for the dismantling and disposal of the turbines under one procurement. âWe could, under Chapter 30.39M, which was the way the turbines were put up, have a procurement that goes out for the removal and disposal of the turbines,â Mr. Morog said. âThe bidder, the successful bidder, whether they are paying us an amount of money or we have to pay them to have them removed, would be able to do what they like with them, if they are the lowest responsible bidder.â