(MANILA BULLETIN FILE PHOTO) In a statement on Thursday, March 4, the Light Rail Transit Authority (LRTA) said the line’s East Extension Project is already 93.42 percent complete as of Jan. 31 this year. LRTA Spokesperson Hernando Cabrera said the two additional stations – Emerald Station in Marikina City and Masinag Station at the Masinag Junction in Antipolo City – will have a soft opening on April 26 and will immediately start operations the next day. In a project briefing and concourse walk-through of the line’s station in Marikina last January. Transportation Secretary Arthur P. Tugade pushed for the immediate completion of the new stations to benefit more commuters amid the pandemic.