Minnesota Court of Appeals affirms Line 3 pipeline replaceme

Minnesota Court of Appeals affirms Line 3 pipeline replacement


(The Center Square) – The Minnesota Court of Appeals on Monday affirmed the state’s Public Utilities Commission approval of the Line 3 Replacement Project.
The Court of Appeals determined the MPUC’s approval of the Line 3 environmental impact statement, certificate of need and route permit were accurate.
The 337-mile new pipeline replaces 283 miles of the current Line 3, and will span Minnesota from the North Dakota border to the Wisconsin border.
“After six years of community engagement, environmental review, regulatory and legal review, it’s good to see confirmation of previous decisions on the Line 3 Replacement Project,” Vern Yu, Enbridge executive vice president and president Liquids Pipelines. “From the start, the project has been about improving safety and reliability for communities and protecting the environment.”

Related Keywords

Minnesota , United States , Wisconsin , North Dakota , Minnesotans , Brent Murcia , Lucindae Jesson , Vern Yu , Peterm Reyes Jr , Winona Laduke , Margaret Levin , Public Utilities Commission , Center Square , Sierra Club , Minnesota Public Utilities Commission , Minnesota Court , Enbridge , Sierra Club North Star Chapter , Judge Lucinda , Appeals Judge Peter , Youth Climate , President Biden , மினசோட்டா , ஒன்றுபட்டது மாநிலங்களில் , விஸ்கான்சின் , வடக்கு டகோட்டா , ப்ரெண்ட் முர்சியா , வர்ந் யூ , வினோனா ளடுக்கெ , மார்கரெட் லெவின் , பொது பயன்பாடுகள் தரகு , மையம் சதுரம் , சியரா சங்கம் , மினசோட்டா பொது பயன்பாடுகள் தரகு , மினசோட்டா நீதிமன்றம் , என்பிரிட்கே , சியரா சங்கம் வடக்கு நட்சத்திரம் அத்தியாயம் , நீதிபதி லூசிண்டா , முறையீடுகள் நீதிபதி பீட்டர் , இளைஞர்கள் காலநிலை , ப்ரெஸிடெஂட் பிடென் ,