Rookwood Weir maximum yield increased at cost of $15m : vima

Rookwood Weir maximum yield increased at cost of $15m


An extra $15 million will be spent to increase Rookwood Weir's maximum medium priority yield by 10,000ML, but Capricornia MP Michelle Landry said she would "still fight" for the originally-conceived high yield amount.
The state and federal governments announced today that Sunwater and the companies involved in constructing the weir decided to raise its crest height by 0.7m, bringing the medium priority yield figure to 86,000ML.
The governments will pay for the extra work with $7.5 million each, bringing the total cost of the project to $367 million.
Member for Capricornia Michelle Landry.
Ms Landry said the State Government had "finally seen sense" and committed to spending more money on Rookwood Weir.

Related Keywords

Brisbane , Queensland , Australia , Capricornia Michelle Landry , Annastacia Palaszczuk , Michelle Landry , Labor Party , Rookwood Weir , Capricornia Michelle , State Government , Queensland Government , Real Rookwood Weir Rally , Gladstone Area Water Board , Water Minister Glenn , Water Minister Glenn Butcher , Glenn Butcher , Sun Water , பிரிஸ்பேன் , குயின்ஸ்லாந்து , ஆஸ்திரேலியா , மகர மைக்கேல் லாண்ட்ரி , மைக்கேல் லாண்ட்ரி , தொழிலாளர் கட்சி , ரூக்வுட் வீர் , மகர மைக்கேல் , நிலை அரசு , குயின்ஸ்லாந்து அரசு , ரியல் ரூக்வுட் வீர் பேரணி , மகிழ்ச்சியான கல் பரப்பளவு தண்ணீர் பலகை , தண்ணீர் அமைச்சர் க்ளென் , தண்ணீர் அமைச்சர் க்ளென் கசாப்புக்காரன் , க்ளென் கசாப்புக்காரன் , சூரியன் தண்ணீர் ,