When will Gipsy Patch Lane reopen? Date pushed back as Metrobus works delayed South Gloucestershire Council has shared an update on the project timetable THE BIGGEST STORIES ACROSS BRISTOL IN YOUR INBOXInvalid EmailSomething went wrong, please try again later. SIGN UP When you subscribe we will use the information you provide to send you these newsletters. Your information will be used in accordance with ourPrivacy Notice. Thank you for subscribingWe have more newslettersShow meSee ourprivacy notice Major road disruption in Stoke Gifford could continue all year as a new Metrobus route is built. The road below Gipsy Patch Lane railway bridge was expected to reopen in July this year, but this could potentially be pushed back until December due to flood prevention works.