Auckland's $73m seawall strengthening finished ahead of deadline, under budget
Auckland's $73m seawall strengthening finished ahead of deadline, under budget 3 Feb, 2021 05:00 AM 5 minutes to read Auckland's 600m-long Quay St seawall strengthening project was completed a fortnight ago, beating its projected deadline and coming in up to $2 million under budget. Eric van Essen, Auckland Transport's downtown programme director, said today the Ferry Basin seawall project had met the completion target in mid-January. The job was due to finish in either January or February so it was done early. SEAWALL "My understanding is that we're coming in under budget a...