Construction Stormwater Enforcement: Commonwealth of Massachusetts and Solar Array Developer Enter into Consent Decree | Mitchell, Williams, Selig, Gates & Woodyard, P.L.L.C.


Federal Clean Water Act
Massachusetts Clean Waters Act
The CD provides that Dynamic is the lessee, developer, project proponent and general contractor in an 18.5 acre commercial solar array (“Array”) in Williamsburg, Massachusetts.
The Array is also stated to include the use of, and improvements to, an access road that connects along with the planned installation of a utility connection.
The Massachusetts Attorney General alleged in a previously filed Complaint that certain Dynamic activities related to the construction of the Array resulted in excessive sediment discharges to the West Branch of Mill River and Rogers Brook and their associated tributaries and wetlands resource areas. Such activities are alleged to have violated the previously referenced federal and state statutes and their implementing regulations. ....

United States , Rogers Brook , Mill River , Commonwealth Of Massachusetts , West Branch Mill River , Dynamic Energy Solutions , Office Of The Attorney , United States District Court , Branch Mill River , Branch Of Mill River , Attorney General , Consent Decree , Massachusetts Attorney General , West Branch , Stormwater Pollution Prevention Plan , Massachusett General Fund , ஒன்றுபட்டது மாநிலங்களில் , ரோஜர்ஸ் சிற்றாறு , ஆலை நதி , காமன்வெல்த் ஆஃப் மாசசூசெட்ஸ் , மேற்கு கிளை ஆலை நதி , மாறும் ஆற்றல் தீர்வுகள் , அலுவலகம் ஆஃப் தி வழக்கறிஞர் , ஒன்றுபட்டது மாநிலங்களில் மாவட்டம் நீதிமன்றம் , கிளை ஆலை நதி , கிளை ஆஃப் ஆலை நதி ,

Solar farm ordered to pay $1M for polluting wetlands, river


Stormwater from the site eroded the hillside, filled in wetlands and streams and polluted the branch of the river with what was equivalent to more than an acre of sediment, prosecutors said.
“The impacts to the wetlands and wildlife habitat areas were not only egregious, they were entirely avoidable,” Michael Gorski, director of Mass Department of Environmental Protection’s Western Regional Office in Springfield, said in a statement Monday. The office had investigated pollution at the site, issued remediation orders and eventually, referred the case to the attorney general’s office, the newspaper reported.
“We look forward to completing restoration work at the site, and to placing land into conservation to help protect Massachusetts’ natural resources,” Tony Orr, general counsel for Dynamic Energy Solutions, told the newspaper. ....

United States , West Branch Mill River , Tony Orr , Michael Gorski , Dynamic Energy Solutions , Washington Times , Branch Mill River , Energy Solutions , Daily Hampshire Gazette , Umass Department , Environmental Protection , Western Regional Office , ஒன்றுபட்டது மாநிலங்களில் , மேற்கு கிளை ஆலை நதி , டோனி ர் , மைக்கேல் கோர்ஸ்கி , மாறும் ஆற்றல் தீர்வுகள் , வாஷிங்டன் முறை , கிளை ஆலை நதி , ஆற்றல் தீர்வுகள் , தினசரி ஹாம்ப்ஷயர் கஸெட் , நிறை துறை , சுற்றுச்சூழல் ப்ரொடெக்ஶந் , மேற்கு பிராந்திய அலுவலகம் ,