Vimarsana
Biggest News Aggregation in the World

Contractor Coordination News Today : Breaking News, Live Updates & Top Stories | Vimarsana

Stay updated with breaking news from Contractor Coordination. Get real-time updates on events, politics, business, and more. Visit us for reliable news and exclusive interviews.

Top News In Contractor Coordination Today - Breaking & Trending Today

Maine South High School - March 2021 Construction Update - Vimarsana News

Maine South High School - March 2021 Construction Update

Maine South High School   Current Progress Maine East:  Field House finishes continue toward completion.  2nd Floor Fitness Room flooring is ongoing as is casework and finishes in locker rooms.  Elevator installation is wrapping up as is HVAC systems as we move toward completion.  Progress continues to maintain schedule. Sitework around the addition scheduled to commence over the next few weeks weather dependent. The Center Court (Area E) demolition is wrapping up.  Mechanical, electrical, plumbing and fire protection installation is ramping up.  Steel install for the new skylight open...

Maine South High School - February 2021 Construction Update - Vimarsana News

Maine South High School - February 2021 Construction Update

Maine South High School   Current Progress Maine East:  The fieldhouse is fully enclosed and finishes are underway. Finishes includes painting, ceiling installation and epoxy flooring in the locker room areas. 2nd floor overhead duct installation is progressing and should wrap up in next few weeks. Progress continues to maintain schedule. The Center Court (Area E) has been fully abated and demolition is underway.  Demolition will wrap up by end of February.  Mechanical, electrical, plumbing and fire protection layout has already started and will begin installation over next 2 weeks. The F...

Maine South High School - January 2021 Construction Update - Vimarsana News

Maine South High School - January 2021 Construction Update

Maine South High School PROJECT SUMMARY Current Progress Maine East:  Field House windows are wrapping up which makes the addition weather tight. Mechanical, electrical, plumbing and fire protection trades are ongoing on both floors of the addition. 1st floor is substantially roughed in and ceiling system / finishes are commencing.  Progress continues to maintain schedule. The Potter Wing renovation project has been turned over to the District.  Punch List activities are underway. The 2nd portion of 3rd floor C wing is wrapping up and will be turned over for District’s use after the 1st ...

Maine South High School - December 2020 Construction Update - Vimarsana News

Maine South High School - December 2020 Construction Update

Maine South High School PROJECT SUMMARY Summer Construction 2020 Continue to complete punch list activities, commissioning and close out documents at each school currently.  Progress of ongoing work by school is listed below. Maine East:  Field House Brick Veneer is wrapping up.  Windows and exterior glazing will commence over the next few weeks.  Mechanical, electrical, plumbing and fire protection trades have all started work inside the addition.  Progress continues to maintain schedule. The Potter Wing renovation project is being wrapped up.  Final details and punch listing is on goi...