Maine South High School - March 2021 Construction Update
Maine South High School Current Progress Maine East: Field House finishes continue toward completion. 2nd Floor Fitness Room flooring is ongoing as is casework and finishes in locker rooms. Elevator installation is wrapping up as is HVAC systems as we move toward completion. Progress continues to maintain schedule. Sitework around the addition scheduled to commence over the next few weeks weather dependent. The Center Court (Area E) demolition is wrapping up. Mechanical, electrical, plumbing and fire protection installation is ramping up. Steel install for the new skylight open...