SFGTV August 31, 2014
Item 13 approve an increase in the construction contract cost contingency for contract no. Wd2685, with cal state contractors inc. , for reservoir and tanks improvement 20133, in the amount of 682,000; and authorize the general manager to approve future modifications to the contract for a total revised contract amount up to 9,997,900. The requested increase is due to new Water Conservation work requested for twin peaks reservoir. The work includes preparing and installing new water barriers along all submerged concrete slab joints to inhibit water leakage from the reservoir to its underdrains....