Phase 2 begins in Ohio County Bridges Project, closing parts of I-70 eastbound
Phase 2 begins in Ohio County Bridges Project, closing parts of I-70 eastbound By February 1, 2021 - 12:41 pm WHEELING, W.Va. — Motorists in the Wheeling area might be experiencing Déjà vu on Monday and for the next nine months. The second phase of the $214-million bridge rehabilitation project on Interstate-70 through Ohio County began at 10:30 a.m. Monday as I-70 eastbound was closed by Swank Construction from Exit 1B, the U.S. 250/W.Va. Rt. 2-16th Street exit, to Exit 2A, the Oglebay Park exit. The first phase of the project, which featured a demolition of the Fulton Bridge, began ne...