SFGTV November 22, 2014
Slightly ahead of schedule and keep it on the trailer and park the trailer in the storage lot and bring it out to the project as they need it. And obviously it is close timing between feeding the project with the steel arriving and because we dont have especially for the size of the elements we dont have the storage on site, later when the train gets poured and the floor slab for the finished trades there will be more room to stage the material on there and the bus deck and the roof deck for the specific activity and not for the structural steel. That is what makes it more complex, and a lot h...