SFGTV February 19, 2013
And there are also significant risks remaining on that project. So, we are at the same time negotiating a final change order for the discovery of those features with the contractors. All that to say that we will need to go back to our commission and to this committee in about april or may. We will come back and seek from you an approval for additional revisions to the program costs. Now, any increases in the program on that project in the program, we will want to compensate by with savings. So, at the same time we are undertaking a very comprehensive assessment of all remaining projects with t...