I-83 Mount Rose contractor says project moving 'as expeditiously as possible'
View Comments It's now 918 days behind schedule, but the contractor working on the much-criticized Interstate 83 Mount Rose makeover says it's progressing "as expeditiously as possible." Tutor Perini, the parent company of Cherry Hill Construction of Jessup, Md., issued a statement Tuesday in response to recent news media reports about the reconstruction of the interchange, which has become the butt of jokes for many in the region. In the statement, the contractor says the state Department of Transportation hasn't reviewed its plans for paving the highway, and it's one of the delays that can...