Maine Supreme Court rules in favor of CMP's lease for power line
The state's highest court on Tuesday found that Central Maine Power had a valid lease of public land that would be crossed by the New England Clean Energy Connect project.
Stay updated with breaking news from Johnson Mountain. Get real-time updates on events, politics, business, and more. Visit us for reliable news and exclusive interviews.
The state's highest court on Tuesday found that Central Maine Power had a valid lease of public land that would be crossed by the New England Clean Energy Connect project.
In a ruling Tuesday morning, Maine's Supreme Judicial Court said that the state "acted within its constitutional and statutory authority" when granting CMP a lease through state-owned lands in 2020. The lease accounts for only a small part of the 145-mile-long transmission line.
In a ruling Tuesday morning, Maine's Supreme Judicial Court said that the state "acted within its constitutional and statutory authority" when granting CMP a lease through state-owned lands in 2020. The lease accounts for only a small part of the 145-mile-long transmission line.
The Supreme Judicial Court finds that Central Maine Power has a valid lease of public land that would be crossed by the New England Clean Energy Connect project.
The Supreme Judicial Court finds that Central Maine Power had a valid lease of public land that would be crossed by the New England Clean Energy Connect project.