More delays and more costs for upgrade of city hall's fire escape | News, Sports, Jobs
YOUNGSTOWN — It’s not going to be until late February or early March — along with at least $200,000 more in costs — before the city hall fire escape is
Stay updated with breaking news from Murphy Contracting Co. Get real-time updates on events, politics, business, and more. Visit us for reliable news and exclusive interviews.
YOUNGSTOWN — It’s not going to be until late February or early March — along with at least $200,000 more in costs — before the city hall fire escape is
YOUNGSTOWN — Work to replace the city hall fire escape, closed since March 9 because of safety problems, should begin in late October. The work should
YOUNGSTOWN — The company that did repair work to the city hall fire escape submitted the apparent lowest proposal to replace it. The city opened bids Friday
YOUNGSTOWN — Greatly increasing the cost of replacing the city hall fire escape to up to $1.1 million and approving $416,040 in American Rescue Plan projec
YOUNGSTOWN — Work to the city hall fire escape that has limited public access to the building should be done in a month to 45 days, but the cost of the projec