Crossrail reveals best and worst case scenarios for Elizabeth line opening date
In its latest publicly available Project Representative report, Jacobs is critical of senior management “aspirations” for delivering the Elizabeth line. It states: “To date, it is evident that schedule planning and delivery is heavily influenced by senior management aspirations for the earliest opening of the Elizabeth Line. […] With key strategic risks now materialising, realistic productivity measures to underpin the schedule will be difficult to derive. “Continued planning to target dates will drive out-of-sequence working and deferral of works that will require operational restr...