Weld Board of Appeals affirms AT&T cellphone tower permit
According to the Board of Appeals ruling, specific requirements not met included: • The September meeting was plagued with technical difficulties such that Planning Board members and attendees couldn’t hear one another. • Roll call votes, required by state law, weren’t taken. • The Planning Board failed to address each of the nine standards included under Article 21, the commercial and industrial structures section of the Weld Building Ordinance. • The Planning Board concluded incorrectly that the deed AT&T submitted showed sufficient proof of right title and interest. Later that ...