Team DFC Targets Completion Of Valsad ROB In 20 Days With Innovative Approach, Despite Big Constraints


Team DFC Targets Completion Of Valsad ROB In 20 Days With Innovative Approach, Despite Big Constraints
by Arun Kumar Das - Jun 6, 2021 04:40 AM
Team DFC at work on the Valsad ROB in Gujarat.
Snapshot
The ROB work could not be started due to various limitations, as track laying activities using state-of-the-art New Track Construction machines would have been affected.
The biggest challenge in doing this work was the road traffic block, as this ROB is one of the busiest passages into the city of Valsad from Mumbai-Delhi highway.
Looking at difficulties during the pandemic as an opportunity for transformation, Team DFC has initiated an innovative out-of-box approach to complete the work on the Valsad Road Over Bridge (ROB) in Gujarat on the Western Dedicated Freight Corridor with minimal traffic disruption. ....

Uttar Pradesh , Jawaharlal Nehru , Indian Railway , Valsad Road Over Bridge , Western Dedicated Freight Corridor , New Track Construction , Dedicated Freight , Western Corridor , Jawaharlal Nehru Port , Indian Railways , Dedicated Freight Corridor Corporation , Rail Overbridge , Dedicated Freight Corridor , உத்தர் பிரதேஷ் , ஜவஹர்லால் நேரு , இந்தியன் ரயில்வே , மேற்கு அர்ப்பணிப்பு சரக்கு தாழ்வாரம் , புதியது டிராக் கட்டுமானம் , அர்ப்பணிப்பு சரக்கு , மேற்கு தாழ்வாரம் , ஜவஹர்லால் நேரு போர்த் , அர்ப்பணிப்பு சரக்கு தாழ்வாரம் நிறுவனம் , ரயில் ஓவர்‌ப்ரிட்ஜ் , அர்ப்பணிப்பு சரக்கு தாழ்வாரம் ,

Lockdown Pinches: Despite Limited Labour Availability, Railways Expedites Work On Dedicated Freight Corridors


Lockdown Pinches: Despite Limited Labour Availability, Railways Expedites Work On Dedicated Freight Corridors
by Arun Kumar Das - May 24, 2021 04:33 AM
The NTC machine.
Snapshot
Currently, there are 15,291 people working in the biological bubble to carry out the rail laying and other related work to make both the Eastern and Western Corridors fully operational for exclusive freight train operations in the country.
Defying heavy odds, work on the Dedicated Freight Corridor is going on with limited workforce of about 15,000, while goods trains are picking up maximum speed up to 97 kmph on the completed section.
Currently, there are 15,291 people working in the biological bubble to carry out the rail laying and other related work to make both the Eastern and Western Corridors fully operational for exclusive freight train operations in the country. ....

Uttar Pradesh , Jawaharlal Nehru , Chiraila Pauthu , Railway Authority , Indian Railways , Dedicated Freight Corridor , Western Corridors , New Palanpur , New Ganj Khawaja , Chiraila Pauthu Section , Dedicated Freight , Western Corridor , Jawaharlal Nehru Port , Dedicated Freight Corridors , Covid 19 , உத்தர் பிரதேஷ் , ஜவஹர்லால் நேரு , ரயில்வே அதிகாரம் , இந்தியன் ரயில்வே , அர்ப்பணிப்பு சரக்கு தாழ்வாரம் , மேற்கு தாழ்வாரங்கள் , புதியது பலன்பூர் , அர்ப்பணிப்பு சரக்கு , மேற்கு தாழ்வாரம் , ஜவஹர்லால் நேரு போர்த் , அர்ப்பணிப்பு சரக்கு தாழ்வாரங்கள் ,