8 April 2021
Major new transmission network projects are now in doubt after the Australian Energy Market Commission formally rejected a request from network companies to allow for increased early revenues from key network upgrades.
The decision could potentially kill off plans to build major new network links identified in the Australian Energy Market Operator’s Integrated System Plan, considered crucial for further investment in wind and solar projects and the transition to a renewables-dominated grid.
Network companies had been hoping to front-end revenues to aid in securing finance for the network projects. Transgrid and ElectraNet said was necessary to ensure finance could be secured.

Related Keywords

Orana ,Western Australia ,Australia ,Cambridge ,Cambridgeshire ,United Kingdom ,Sydney ,New South Wales ,Australian ,Michael Mazengarb ,Renewable Energy Zones ,Cambridge Economic Policy Associates ,Australian Energy Market Operator Integrated System Plan ,Energy Distribution Network ,Australian Energy Market Commission ,National Electricity Market ,Central West Orana Renewable Energy Zone ,Australian Energy Market Operator ,Integrated System Plan ,Project Energyconnect ,South Australia ,New South ,System Plan ,Transmission Infrastructure Strategy ,ஓரண ,மேற்கு ஆஸ்திரேலியா ,ஆஸ்திரேலியா ,கேம்பிரிட்ஜ் ,கேம்பிரிட்ஜ்ஷைர் ,ஒன்றுபட்டது கிஂக்டம் ,சிட்னி ,புதியது தெற்கு வேல்ஸ் ,ஆஸ்திரேலிய ,புதுப்பிக்கத்தக்க ஆற்றல் ஸோந்ஸ் ,கேம்பிரிட்ஜ் பொருளாதார பாலிஸீ கூட்டாளிகள் ,ஆஸ்திரேலிய ஆற்றல் சந்தை ஆபரேட்டர் ஒருங்கிணைந்த அமைப்பு திட்டம் ,ஆற்றல் விநியோகம் வலைப்பின்னல் ,ஆஸ்திரேலிய ஆற்றல் சந்தை தரகு ,தேசிய மின்சாரம் சந்தை ,மைய மேற்கு ஓரண புதுப்பிக்கத்தக்க ஆற்றல் ஸோந் ,ஆஸ்திரேலிய ஆற்றல் சந்தை ஆபரேட்டர் ,ஒருங்கிணைந்த அமைப்பு திட்டம் ,தெற்கு ஆஸ்திரேலியா ,புதியது தெற்கு ,அமைப்பு திட்டம் ,பரவும் முறை உள்கட்டமைப்பு மூலோபாயம் ,

© 2025 Vimarsana

vimarsana.com © 2020. All Rights Reserved.