The latest cost projection for the entire project is $94 million, based on the $36.8 million the village had spent as of two years ago and the $57.2 million in additional borrowing. The village so far has installed 6.5 miles of 24-inch-diameter transmission mains across Woodbury and tapped a well in Mountainville. That bountiful new source - capable of furnishing 612,000 gallons of water per day - has expanded the groundwater supply for Kiryas Joel's growing population while the village continues its aqueduct project. The next four miles of pipeline are scheduled to be completed by April 2022. The village has not laid out a timetable yet for the remaining 3.5 miles or said if the work will continue north on Route 32 or detour onto Holloran Road, which would require the Town of Cornwall's permission.