By Ifham Nizam The Power Ministry will go all out to complete the 35MW Broadlands Hydro power plant next month especially to cut down expensive oil fired power generation and avoid emergency power purchases. The plant was scheduled to be completed last December but it got delayed due to the non- availability of top Chinese experts owing to the pandemic, but, with their return, the Ministry is confident of getting it completed now. Forty five Chinese experts are in the process of completing the plant. With the commissioning of the plant, the CEB would be able to save more than Rs. 10 million a day. In 2020, CEB losses were Rs. 60 billion as against Rs 85 billion in the previous year, a senior official said.