SFGTV July 30, 2014
Come back and we expect to get another 20 years out of them. Were only going to be taking four cars out of service at a time, so, service wont be affected during the project. The contract is with brookville equipment, Contract Value is 34. 4 million. And if you have any questions, wed be glad to answer them. Okay, thank you. Colleagues, no questions . Mr. Row, can we go to your report, please . Yes, mr. Chairman, supervisor mar. On page 4 of our report, a budget for the proposed project costs will be 34. 5 million as shown in table 3. And, again, thats on page 4 of our report. And then on page...