Out the request for the demolition and how long does that take . Sf public works has an asneeded contract that were using so were not facing a typical process for this demolition work. We can tap into that already contract. So thats not the timeline that we should be worried about. The actual demolition work i think is not that complicated, may take a month to two months in terms of the actual work stating the work, putting up the protective fencing and actually doing the demolition work. So the amount of time it takes to demolish can easily be accomplished between now and widas need for this ...