SFGTV May 25, 2015
Graphs for the month to month. Thank you deputy if that report. Any Public Comments, on items ad. . Seeing none [inaudible]. Good afternoon, commissioners, im the project manager for the accela project the functional items of the system development. We have eight of the 21 punch list items that are remaining, finish and ready to test we started the testing of those remaining items part of the uat that testing started last week will continue this week and next and continue to test the remaining items, on the 21 item list without the remaining weeks in may, as well as mid july, when the balance ...